The 60 day fabrication of two large cofferdams with a combined weight of about 240 tons was a complete success. The design of the Cofferdam structure, operation and logistic took 3 months and was a collaboration between the GB Shipyard, RCCL, ABB & QSL. General Info: • 2 Cofferdams
• QSL Senior Designer worked directly with Royal Caribbean related companies. • Start Fabrication: Mid December 2013 • Finished Fabrication and delivery: Mid February 2014 Logistic: Transport of Cofferdams from QSL shop to GB Dry Dock and Set in Position on Dock • Equipment used for this operation:
• Heavy Duty Dollies • Ramp System (shore to Barge & Barge to Dock) The job was carried out safely, without a lost time accident. |